True to its name, the portion of the house heated by 'furnace 2' got down to a chilly 49 overnight as Dale was unable to get the part he needed to fix the brand new furnace in the basement which quit yesterday. He returned this morning and was able to correct the problem and we had gained about 10 degrees in the first hour after it began working. We are back to normal now, and cautiously watching the others for additional citrus signs. (Lemons?)
The concrete guys stopped by long enough yesterday morning to drop off blankets and tuck in the walls. With temps dipping into the twenties over night they needed to keep it hot enough to cook (cure.)
Glen is moving along on the tile. Tommy happily crawls into the floor every morning when Glen arrives and I don't see him until the house is quiet at 6:00 pm.
The electricians, (bless their hearts,) are hard at work completely re-wiring the kitchen. They've been here three days straight and have still some more work to do. It's taking much more time than I anticipated but as an added bonus, they managed to fix the call button box when they were fixing the doorbell. They work a bunch in Oakwood, and while they had seen call buttons before, they were quite excited to see that they were still operable and hooked up to the original mechanical box. They'd never seen that before.
Payne and Co., (the drainage people,) have their liliputian equipment stationed out by the living room and are making good progress on the excavation there. Their back-hoe is so cute! Rob's guy will be patching the holes in the foundation with some hydrostatic cement, then the whole thing will be water-proofed, gravel and drain tiles installed, all the drains and down spouts tied in and then back-filled to grade. Again a bonus, the arbor vitae I dislike had to be torn up to facilitate the excavation.
When Rob took out the windows in the girls' bathroom, he fitted the hole with a 1/4 piece of bead-board plywood. It was over 85 degrees in the bathroom this morning, testament to the amount of heat we are losing through the darn windows. Dan says we have a solution... just cover them all up with plywood!
I did meet with a storm window guy yesterday and that option looks better and better. More on that later.