This morning as I was making Cocoa for the girls, I saw our mouse. Rather, I saw a streaking blur out of the corner of my eye darting from under the fridge to under the stove - I couldn't really see it as it was going about 240 miles per hour. I called to Tommie-Cat, disturbing his breakfast. He looked at me like "whatever..." and went back to his 'cat beans' (as Naomi calls his food.)
We have contracted for storm windows for the dining room and living room. It'll be six weeks, just in time for spring!
I'm headed to Lexington this weekend with the girls, Dan is staying put to work on the bathroom. (We're responsible for painting it.) If he doesn't get it done, I'll release Rob to get on it next week. I am eager to push it along since the tub in the master bath (which we are NOT re-doing any time soon,) kind of blew out this week. Korrect Plumbing (my heroes) were able to get it back together, even 'though Dan, who harbors a secret desire to be a plumber, got to it first and essentially trashed it. Thank goodness we saved the tub valve out of the girls' bathroom - the plumber stripped the seats and stems off of it to make our tub work. But that valve won't last for long so we need to get the other tub up and running for the girls. Dan and I can survive without a tub since we have the separate shower, but the kids really need one.
I finally got a plan out of one of the landscape contractors. It wasn't at all what I wanted, so it's back to the drawing board. (Not that I can even fathom doing yard work in this cold.) Looking ahead... looking ahead....
Dan and I came across an article about retro fitting insulation in older homes. After the weather this week, we are intrigued by it. I'll point it out to Rob for his opinion when I next see him.
I've only had one taker on the gas bill pool. (See my last post.) Let me know if you are interested!
Showing posts with label plumbing. Show all posts
Showing posts with label plumbing. Show all posts
Friday, February 9, 2007
Monday, January 8, 2007
This cOld House 13



Well, happy birthday to me!
Right now at my house I have a tile guy, a plumber, four electricians, a whole crew of concrete guys, my G.C., his carpenter and the drainage guys are on their way. To paraphrase Steve Martin in The Jerk, "Things are gonna start happening here now!"
I was not expecting the electricians today, and had I known they were coming, I probably wouldn't have worked so hard to remove debris on the floor this weekend. They have a couple of days work so I really shouldn't clean up until later in the week. The wood floors are taking a beating from the rubble, (plaster dust, sand and chunks,) and we are trying to mitigate damage by wiping up every night. It is, however a Sysyphian task.
The good news is that we can now plug in them modrun new-fangled thangs (like a DVD player) in the girls' room. Also, I should have plugs that work without kicking off breakers in the kitchen, light switches that control only the lights, not every outlet in the room, power to the pool house, more than one phone outlet, and the ability to use the lap-top in the living room by the end of the week.
With lath and plaster houses, the metal mesh they lay over the lath strips to hold the plaster wreaks havoc with wireless signals. The cordless phone only works in half the house, the computer's wireless router only reaches to the dining room, and when the guys are working in the basement they have to turn their phones off or they go dead in an hour from frantically trying to find a network.
Tommy Cat has broadened his domain to include crawling in behind the walls in the bathroom we have all tore up and getting up under the eaves, where he has discovered a loose floor board leading to the 10 inch space between the girls' bedroom floor and the ceiling below in the dining room. He disappears for hours at a time and emerges a completely different color than when he went in. We have a black smudge on our bed cover from his nocturnal forays and returns. When we pet him, our hands turn black. We did attempt to block him out of the bathroom but he meows like a fiend when he can't get in and has actually found another way to get there. Rather than fight it, we are letting him go. He also found his way into the pipe chase in our bedroom to the master bath, but we've managed to dissuade him from there by leaving the other bathroom open. The mouse poop in the kitchen has been diminishing all week and I did not find any this morning.
The concrete guys passed their inspection this morning and they are pouring walls right now.
Rob managed to pull the girls' bathroom windows out, so we now have a clear look at how bad the water damage on the sill is. It's BAD! We will be pulling the whole window frame out and rebuilding it to the dimensions of the not-yet-discovered solution to the window problem. I have another window guy looking next week - a restoration specialist from Cinci.
I will post now because I'm so excited, and add pictures later when the electricians stop cutting power indiscriminately.
Thursday, December 14, 2006
This cOld House 8
Today I had the pleasure of meeting Dewayne, Electrical Inspector for the Neighboring City to Pleasantville, (who does the Pleasantville construction inspections.) Unfortunately, he had nothing good to say about the power in my kitchen. He had deja vu when he pulled up to the house to inspect the new panel we put in last week, and when I got to talking to him about some apparently open issues that the City of Oakwood cited us on our property transfer inspection, he started to recall the disastrous inspection he carried out here when the kitchen was redone. (And that he was never recalled to final the stuff, presumably because it was never corrected.) I am currently awaiting a copy of his laundry list.
Tim and Troy and Matt are wreaking havoc in the basement, pulling out galvanized pipe to beat the band. Tim said there was a LOT of pipe, like three times what we actually needed. This is good news since we opted to NOT install the recirculating pump on the hot water heater. So while it currently takes about 2 minutes for hot water to make it up to our bathroom, it should be cut in less than half when we replace the pipes with a more direct route.
The bid came in for the new gas service/pipes and it's a go. We'll do that as soon as we have a front wall on the new garage so we can attach the new meter.
The concrete guy happened to show up at the same time Mark came by to grind out the stumps from the trees we took down Tuesday and they had a meeting of the minds, so we are all set to start digging TOMORROW or Monday. I'm so excited! By the way, watching the 'lumberjacks' take down the trees was a thing of beauty. It was like a ballet the way the guys all knew their moves and jumped in and out to get it done smoothly and safely. And today the stump grinder kicked butt! I want to grind stumps when I grow up. Mark has one of only 2 in Ohio and 340 in the entire country, a stump grinder that just freakin' ATE the tree. It was like a 20 inch circular saw on the front that swept back and forth decimating anything in its way. The teeth on the blade were about 3 inches long! Very cool to watch.
I got the bid on restoring the windows and was NOT happy. I called Rob to get the Pella or Andersen or Marvin guy to come over and discuss replacement options. I also got an e-mail from the garage door guy and am awaiting a bid for that.
By the way, I fixed our garage door that was broken. It was a four dollar and eighty one cent personal victory after thousands and thousands of dollars of defeat this week.
This weekend I believe we get to test drive our squirrel abatement system. I hope Kitty is mean when it comes to wildlife because she has quite a lot of established residents to show who is boss. There is a rotund woodchuck that lives under the pool house, dozens of gray squirrels, (some as big as small cats,) a raccoon, and a hedgehog looking thing that wanders in the dark. Go Kitty Go!
Tim and Troy and Matt are wreaking havoc in the basement, pulling out galvanized pipe to beat the band. Tim said there was a LOT of pipe, like three times what we actually needed. This is good news since we opted to NOT install the recirculating pump on the hot water heater. So while it currently takes about 2 minutes for hot water to make it up to our bathroom, it should be cut in less than half when we replace the pipes with a more direct route.
The bid came in for the new gas service/pipes and it's a go. We'll do that as soon as we have a front wall on the new garage so we can attach the new meter.
The concrete guy happened to show up at the same time Mark came by to grind out the stumps from the trees we took down Tuesday and they had a meeting of the minds, so we are all set to start digging TOMORROW or Monday. I'm so excited! By the way, watching the 'lumberjacks' take down the trees was a thing of beauty. It was like a ballet the way the guys all knew their moves and jumped in and out to get it done smoothly and safely. And today the stump grinder kicked butt! I want to grind stumps when I grow up. Mark has one of only 2 in Ohio and 340 in the entire country, a stump grinder that just freakin' ATE the tree. It was like a 20 inch circular saw on the front that swept back and forth decimating anything in its way. The teeth on the blade were about 3 inches long! Very cool to watch.
I got the bid on restoring the windows and was NOT happy. I called Rob to get the Pella or Andersen or Marvin guy to come over and discuss replacement options. I also got an e-mail from the garage door guy and am awaiting a bid for that.
By the way, I fixed our garage door that was broken. It was a four dollar and eighty one cent personal victory after thousands and thousands of dollars of defeat this week.
This weekend I believe we get to test drive our squirrel abatement system. I hope Kitty is mean when it comes to wildlife because she has quite a lot of established residents to show who is boss. There is a rotund woodchuck that lives under the pool house, dozens of gray squirrels, (some as big as small cats,) a raccoon, and a hedgehog looking thing that wanders in the dark. Go Kitty Go!
Tuesday, December 5, 2006
This cOld House 7
It's been a slow couple of weeks with Dale working in the attic on the new HVAC and nothing much else going on. I met with the plumber and electrician to go over what all our wants/needs are. I had a sitter a couple of afternoons so I could head on down to the tile showroom and pick out something small (and cheap) for the girls' bathroom.
The bid came in for the garage project and it was WAY higher than expected. I keep underestimating most jobs, I suppose because I haven't worked in the industry for a decade or so. I met with the GC and Architect to do some expense control, as well as with our real estate agent to get some guidance on what price he feels this house in this neighborhood can support. He has sold it twice, and knows the area well. I want to pick his brain on what feedback he got from other folks who viewed the house when it was on the market. I'm hoping that the boring stuff we are fixing, HVAC, plumbing, electrical, etc. is the kind of stuff that scared other buyers away, and that we can expect some recompense from these outlays. (Slim chance, but hope springs eternal.)
We did get some nice bids for the girls' bath and the rest of the plumbing. It's a go ahead. And with the temperatures dropping in to the 'teens in the past week, I'm VERY eager to start work on the garage, budget be damned.
I had to fire the electrician today. I was satisfied with neither the work nor the service and he pissed me off one too many times. Back to the drawing board there, with no really good alternative available.
We will be starting on the basement pipes tomorrow. The HVAC is all done except for the A/C which we won't be needing any time soon.
Today the tree guys are here razing my front yard. It will start the neighbors talking for sure! I'm trying to get some good picture in between doing laundry, blogging and keeping the kids fed. I tell 'ya, there's real beauty in watching pros do what they do best.
Last night the garage door jammed. We managed to get it closed, but there will be no more ingress/egress through that route until we are able to either fix it inexpensively ourselves, or replace it altogether with the new wall and double walk thru door.
The bid came in for the garage project and it was WAY higher than expected. I keep underestimating most jobs, I suppose because I haven't worked in the industry for a decade or so. I met with the GC and Architect to do some expense control, as well as with our real estate agent to get some guidance on what price he feels this house in this neighborhood can support. He has sold it twice, and knows the area well. I want to pick his brain on what feedback he got from other folks who viewed the house when it was on the market. I'm hoping that the boring stuff we are fixing, HVAC, plumbing, electrical, etc. is the kind of stuff that scared other buyers away, and that we can expect some recompense from these outlays. (Slim chance, but hope springs eternal.)
We did get some nice bids for the girls' bath and the rest of the plumbing. It's a go ahead. And with the temperatures dropping in to the 'teens in the past week, I'm VERY eager to start work on the garage, budget be damned.
I had to fire the electrician today. I was satisfied with neither the work nor the service and he pissed me off one too many times. Back to the drawing board there, with no really good alternative available.
We will be starting on the basement pipes tomorrow. The HVAC is all done except for the A/C which we won't be needing any time soon.
Today the tree guys are here razing my front yard. It will start the neighbors talking for sure! I'm trying to get some good picture in between doing laundry, blogging and keeping the kids fed. I tell 'ya, there's real beauty in watching pros do what they do best.
Last night the garage door jammed. We managed to get it closed, but there will be no more ingress/egress through that route until we are able to either fix it inexpensively ourselves, or replace it altogether with the new wall and double walk thru door.
Thursday, November 30, 2006
This cOld House 6
The last couple of days have been very very busy around here. Dale started on the attic HVAC unit, cutting through ceilings for duct work and hauling the hardware upstairs to the attic. Hey did you know there's not a scrap of insulation between the attic and the the living space below??? There's a quick fix for some efficiency. I'm waiting on Rob's insulation guy (Rob - my general contractor,) to get me some numbers. Dale was missing today, working on fashioning ducts in the shop which worked out terrifically as the power (and water) was off in the house for most of the day.
Rick,(the carpenter who fixed the living room floor,) Larry and Bob Sr. have been tag-teaming on the beam in the garage. Rick and Larry built three support walls to hold up the cantilevered room over top and then mid-way through the second day Rick and then Bob worked to remove the beam that was all ate up. There were three 2 x 8 planks and a 2 x 4 involved, with one 2 x 8 remaining pretty solid. They replaced the remaining two and the 2 x 4 with three more 2 x 8 planks and hung the joists on hangers. The sub-floor was pretty ate up as well, but we can't really get to it as it is under the wall from above. Bob was confident that it wouldn't be an issue.
Tim the plumber was able to get all the water pipes out of the way, shutting down the downstairs bath until the project is done. He had to move some valves and add a couple to get it isolated and shut off, and then cut and capped the pipes. The electric remained in the way.
Right when Rick was getting down to the nitty-gritty pulling out the beam the electricians showed up. These were replacement electricians as the original guy was too busy to get to the panel to meet Bob's schedule. So Tom and crew swarmed in at noon and cut the power, ripping out the old 200 AMP panel, moving the meter and installing a new 200 AMP panel over by where the new A/C condensers will sit outside the old garage. Then they added a new 100 AMP sub-panel where the old panel was, and hooked up the rest of the house back to it. All of this took care of the main line which had to be moved out of the way of the beam replacement project, as well as various and sundry fire hazards discovered when we ripped down the drywall ceiling in the old garage. Tom is coming by tomorrow to see what all else needs to be done. (Making the plugs kid-safe, fixing the code issues in the kitchen, running new clean power to the A/V and computers, adding a phone jack so we can answer the phone in the living room.) Dan also said something about running some CAT6 (ethernet) around as well.
Rob and Co. (That's the two Rick's, Bob Sr. and Larry, so far,) will have no more to do once the beam is done until I get a firm bid on the new garage and the bathroom remodel. As it is we're about 2 good man-weeks into T & M (time and material) stuff and that makes me nervous. The living room floor had a price tag on it but they found more damage than anticipated, and I have only my own estimation on what the beam will cost us.
Tim the plumber had some good news for us in that we now have a pretty good plan on how to clean up the miles of pipes in the house. The girls bathroom is now a must do, for several reasons, but once it is done, we will have over half the house re-plumbed, (correctly and legally,) including all the supply in the basement. It will be great to get rid of all the old galvanized piping down there as it's corroding as I sit here, waiting to spring a leak. (Not to mention the 17 rusting valves in the laundry room alone.) He managed to replace the main shut off valves, install a pressure regulator and baffle, several angle stops and bring the kitchen gas valve up to code. Unfortunately when he reduced the water pressure from 115 PSI to the recommended 85 PSI, we lost all pressure to the upstairs fixtures. (The cold lines are almost completely corroded shut, which is why doing the girls' bath has moved up the priority list.)
I met with a landscape architect to work up a proposal for the front of the house when we tear it up to put in the garage. He seems to be right on track with what I outlined and I'm sure if he watches his spending, he'll do a bang-up plan for us. I meet with a different landscape architect tomorrow to do it all over again.
My other landscape guy dropped by today, (the one who did the clean-up on the yard) and I grabbed him to talk about the stretch of mud along the back of the house. He's working up numbers for me for putting flagstones down. Dan wants to get a second opinion on the catalpa tree, so I'll be calling around tomorrow to get someone out. It is not an immediate need - we can probably wait a year or two before we have to yank it down.
Today the gutters were cleaned for the last time this season. All the trees are now bare so we no longer have to fear a gutter back-up, (provided we don't have a problem with an ice dam.)
All in all we've had a pretty good week with no real surprises. (Although when Tim grabbed an old recirculating line to indicate it needed to be removed, it broke free of its moorings and fell on his head. He had to temporarily tack it back up.) As it turns out, once the termite-beam was removed, the joists were found to be solid, so we didn't have to replace any of them. I haven't had the heart to tell Rick we still have a soft spot in the living room floor behind a duct that he probably didn't see. (He is nursing broken ribs from a car accident last week and I can't imagine shimmying around my crawlspace would be very good for the ailment.) And Other Rick, (the one who worked on all the doors earlier in the week,) appears to have glued my back door shut, which will have to be freed. That back door really needs to be replaced, but we are holding off on frivolous stuff like that. It works just fine for now, (if you put your shoulder into it.)
I'm actually starting to see some light at the end of the tunnel. Of course, this tunnel is a detour I was forced into on my way to building a garage. Still, it's good we are taking care of these things in such a manner that they shouldn't bother us for another 30 years or so. I'm really quite thrilled that the plumbing has presented itself to be a short term project that won't be nearly as difficult as I had feared. And Dan, who is the voice of reason (budget,) also agrees.
Rick,(the carpenter who fixed the living room floor,) Larry and Bob Sr. have been tag-teaming on the beam in the garage. Rick and Larry built three support walls to hold up the cantilevered room over top and then mid-way through the second day Rick and then Bob worked to remove the beam that was all ate up. There were three 2 x 8 planks and a 2 x 4 involved, with one 2 x 8 remaining pretty solid. They replaced the remaining two and the 2 x 4 with three more 2 x 8 planks and hung the joists on hangers. The sub-floor was pretty ate up as well, but we can't really get to it as it is under the wall from above. Bob was confident that it wouldn't be an issue.
Tim the plumber was able to get all the water pipes out of the way, shutting down the downstairs bath until the project is done. He had to move some valves and add a couple to get it isolated and shut off, and then cut and capped the pipes. The electric remained in the way.
Right when Rick was getting down to the nitty-gritty pulling out the beam the electricians showed up. These were replacement electricians as the original guy was too busy to get to the panel to meet Bob's schedule. So Tom and crew swarmed in at noon and cut the power, ripping out the old 200 AMP panel, moving the meter and installing a new 200 AMP panel over by where the new A/C condensers will sit outside the old garage. Then they added a new 100 AMP sub-panel where the old panel was, and hooked up the rest of the house back to it. All of this took care of the main line which had to be moved out of the way of the beam replacement project, as well as various and sundry fire hazards discovered when we ripped down the drywall ceiling in the old garage. Tom is coming by tomorrow to see what all else needs to be done. (Making the plugs kid-safe, fixing the code issues in the kitchen, running new clean power to the A/V and computers, adding a phone jack so we can answer the phone in the living room.) Dan also said something about running some CAT6 (ethernet) around as well.
Rob and Co. (That's the two Rick's, Bob Sr. and Larry, so far,) will have no more to do once the beam is done until I get a firm bid on the new garage and the bathroom remodel. As it is we're about 2 good man-weeks into T & M (time and material) stuff and that makes me nervous. The living room floor had a price tag on it but they found more damage than anticipated, and I have only my own estimation on what the beam will cost us.
Tim the plumber had some good news for us in that we now have a pretty good plan on how to clean up the miles of pipes in the house. The girls bathroom is now a must do, for several reasons, but once it is done, we will have over half the house re-plumbed, (correctly and legally,) including all the supply in the basement. It will be great to get rid of all the old galvanized piping down there as it's corroding as I sit here, waiting to spring a leak. (Not to mention the 17 rusting valves in the laundry room alone.) He managed to replace the main shut off valves, install a pressure regulator and baffle, several angle stops and bring the kitchen gas valve up to code. Unfortunately when he reduced the water pressure from 115 PSI to the recommended 85 PSI, we lost all pressure to the upstairs fixtures. (The cold lines are almost completely corroded shut, which is why doing the girls' bath has moved up the priority list.)
I met with a landscape architect to work up a proposal for the front of the house when we tear it up to put in the garage. He seems to be right on track with what I outlined and I'm sure if he watches his spending, he'll do a bang-up plan for us. I meet with a different landscape architect tomorrow to do it all over again.
My other landscape guy dropped by today, (the one who did the clean-up on the yard) and I grabbed him to talk about the stretch of mud along the back of the house. He's working up numbers for me for putting flagstones down. Dan wants to get a second opinion on the catalpa tree, so I'll be calling around tomorrow to get someone out. It is not an immediate need - we can probably wait a year or two before we have to yank it down.
Today the gutters were cleaned for the last time this season. All the trees are now bare so we no longer have to fear a gutter back-up, (provided we don't have a problem with an ice dam.)
All in all we've had a pretty good week with no real surprises. (Although when Tim grabbed an old recirculating line to indicate it needed to be removed, it broke free of its moorings and fell on his head. He had to temporarily tack it back up.) As it turns out, once the termite-beam was removed, the joists were found to be solid, so we didn't have to replace any of them. I haven't had the heart to tell Rick we still have a soft spot in the living room floor behind a duct that he probably didn't see. (He is nursing broken ribs from a car accident last week and I can't imagine shimmying around my crawlspace would be very good for the ailment.) And Other Rick, (the one who worked on all the doors earlier in the week,) appears to have glued my back door shut, which will have to be freed. That back door really needs to be replaced, but we are holding off on frivolous stuff like that. It works just fine for now, (if you put your shoulder into it.)
I'm actually starting to see some light at the end of the tunnel. Of course, this tunnel is a detour I was forced into on my way to building a garage. Still, it's good we are taking care of these things in such a manner that they shouldn't bother us for another 30 years or so. I'm really quite thrilled that the plumbing has presented itself to be a short term project that won't be nearly as difficult as I had feared. And Dan, who is the voice of reason (budget,) also agrees.