Thursday, May 29, 2008

This cOld House 35

I started this post a couple of times in the last 6 months, and I'll add those thoughts first so you can see where we were/are.

Oct 10
My posts are becoming fewer and fewer as our work, 'though barely dented, is winding down due to economic forecasts. We are finally coming to the end of the saga of the roof... 9 contracts and 11 months from our first estimate. The Durable guys have been really busting hump on it, and they've been able to with the dry spell we've had the past couple of months.

Durable does mostly slate. When I asked them about the shape of the roof when they started, they commented that they've pretty well seen it all... but generally not all on one roof, until our place. Aluminum substituted for felt as underlayment. Mismatched slates. Slates installed sideways in order to get more run out of it to cover more area... even though it had been pre-drilled for proper installation so the holes showed. Aluminum gutter straps instead of copper slate hooks. Slates with tar, mastic, Great Stuff, mortar, and caulk... what, no duct tape? Slates screwed in with deck and drywall screws. Slate installed with the seams matched, (instead of staggered.) Cracked, delaminated, chipped and shattered slates. Squirrel nests in the ridges. And a 14/12 pitch to boot. Yep... this job had it all. So now, with 12 weeks of work and for the price of a bungelow in any midwestern state, we have a roof that looks much better, stops water from getting in, and will last for about another 70 years. (Or longer with proper maintenance.)

Dec 10
I really haven't much to report. I am happy to tell you that we've been holding water, (on the outside, for a change,) since the roofers got done. We are still waiting for them to finish up the stucco work, but that will probably be hanging out there until spring now.

The new roof does look very nice, and certainly the fact that it no longer rains inside is a bonus. It was an expensive endeavor, slate being more akin to a lifestyle than just a roof, but ultimately it should last another 75 years or so which makes it a worthwhile project.

Rob presented Dan and I with some 'Jahn-wear' last week, part of their frequent buyers club. Larry and Rick have been working in the white house for a couple of weeks. It's starting to shape up. It'll go faster next week after the asbestos abatement is completed and we can get the guys down into the basement to start plumbing, electrical and HVAC.

OK... so that brings us to today, 29May08. I have much to tell but let's start with the fun stuff.

Last weekend Dan and I spent all day Saturday picking up debris around the yard from various projects we've had going. We had quite a lot of fence panels sitting around from where we pulled it all out for the landscaping project this spring, as well as roof and gutter debris to clean up. Also, back behind the pool house was a mess full of weeds, ivy and rotting tree stumps. We were able to clear a lot of that out, and stacked the fence panels back there, out of the way yet accessible for when we figure out what the hell we are going to do with them. By the way, this is the pool house. It's probably only got another year or two before we have to take it down. There is a saddle in the roof and the walls are bowed out from the weight of the slate roof, (for which it was NOT engineered.) Also it sustains a little more water damage from the bottom each year. And we have the problem noted below. We will eventually replace it with a masonry shed to house the pool equipment, wood pile, garden tools and outside toys.

We were pulling nails out of the panels when all of a sudden Dan was in a cloud of what looked like large gnats. We looked around and discovered it was a swarm of termites coming out of an old stump. Termites swarm when the nest becomes too big. Half the colony grabs a queen and splits. I ran for the Raid while Dan smothered the stump with a bag of mulch. The last thing this house needs is a loose swarm of termites looking for a place to nest.

We had already been dealing with a ton of bumblebees around the pool house and I finally got curious and looked up the species on the 'net. Lo and behold our pool house is infested with Carpenter bees What fun! They chew 1/2 inch holes into wood, go about an inch deep then make a 90 degree turn and tunnel another 6 - 10 inches. So now we have termites, Carpenter ants, wood chewing squirrels and Carpenter bees on the property. And our house is made of timbers!

Thursday, July 12, 2007

This cOld House 32






Doors, doors, doors.

While we were on Vacation, Bob got most of the doors finished. The pictures are (left to right, top to bottom,) The screen door for the back hall, the double doors from the old garage to the driveway, the walk through from the new garage to the old garage, the back hall door, the dining room patio doors, and the front screen doors.

I met with a geotech/soils engineer this week and we will be having some testing done to try to pin-point where the water seeping into the basement is coming from. (And more importantly, whether it can be mitigated through some manipulation of the land - swales, drains, etc.) This is really the first step towards addressing the rest of the landscaping. We want to get rid of the bunkers, and while doing so improving the water profile of the property. No question adding plants and trees back will help, but if we can do more, now is the time to incorporate earth movement into the plans.

The work that Durable Slate did before we left, particularly the flashing and copper work around the main chimney, failed to hold water while we were on vacation. We came home to water damage in the attic bedroom, Master bedroom and even some in the living room. That is to say that the leaking, worse than we'd ever experienced, went down through three floors. They sent a guy out as soon as I reported the problem but he was unable to do anything about it because it was raining... (Duh.) A crew will be out today to either finish the work up there, (I was under the impression it had been finished as we'd been charged in full for it,) or to dry it in properly.

We now have a way up to the new patio as Dave has finished the steps from the front porch. I'm eager to get the rest of it completed, which is minimal. (Soldering the seams in the copper counter-flashing, general clean-up including power washing the adjacent brick, and re-pointing said brick, trimming out the electrical and maybe restoring the powder room window.)

I've bugged the new landscaper about getting me a plan this week, which he has promised, but I don't really think it's going to happen. The property is still a mess, the weeds exploding while we were on vacation, and the grass growing tall in spite of my request for mowing.

The pool seems to be holding it's own... although with the prodigious rain it's within an inch of overflowing... (into the laundry room.) Like I keep saying, this house has some seriously bad water mojo.

Rob and Co. are working on Dan's Manspace, (the old garage.) They are building a plywood floor over top of the concrete. There is a 6 inch difference from the bottom of the steps to the house over to where the floor drain was. (The one we capped which went directly into the storm sewer.) This will now be flat, although it will still have some slope to it.




And what's up with THIS place????

Tuesday, June 5, 2007

This cOld House 31

It has been almost a whole month since my last blog and we are moving right along on a number of projects.

Since last month, Bob has been working diligently on several wood projects, the biggest being the posts out back. We removed and refurbished the windows in the girls' room and they look/work great! We have been really pleased with the restoration work Dick at Dayton Art Glass did. Aside from his very competitive price, we get the sense that he enjoys this type of work and puts a lot of care and skill into it. One of the windows needed a complete re-build, but they were able to salvage the glass and match the lead almost perfectly. The good news is, yes, we found the yellow jacket nest. It was located inside the post Bob removed. The post was so rotten that it was almost hollow. Here's an example of what shape the wood was in that Bob removed.That's some fine looking hardwood there! We were unable to find a piece of oak big enough replace the posts, so Bob improvised with two 4 x 8 cedar posts, and then he trimmed on the inside, where needed, with oak to match the original design.

We also had the main gas line replaced, and the new meter mounted on the front of the new garage. It's better than in the basement, but ugly as sin and we're planting some boxwoods around it as soon as possible. All the interior gas lines were replaced at the same time, so now we can actually pass the HVAC inspection. The bad news, (of course) is that none of the fireplace lines held test so they had to completely disconnect them to pass the gas inspection and we now have no gas to the fireplaces. We'll address that at a later date, once we get an assessment of the chimneys.

The other big project this month has been the 'Great Wall' which has taken about all month. The other day the mailman asked the wall guys if they wanted him to forward their mail to here. I told them another week and I'd start charging rent. They are doing beautiful work and we are very pleased with how it looks. Initially we wanted a rock wall, to replace the one that the backhoe split apart, but it was infeasible, (read that - way too expensive in this day and age!) so we settled for a landscape block and were relieved to discover our misgivings about the institutional look of the block were pretty well dashed. They had to haul off about half a dozen trucks of fill and we ended up with two full tiers. It's been slow going, and we've had some set backs, not the least of which was Mike digging up the brand new gas line, not once, but TWICE! I noticed when I did the pictures for this post that Mike was wearing the same shirt both times he hit the line (a week apart) so I told him to get rid of the unlucky t-shirt and bury it when they backfilled the second repair. Thank goodness he doesn't have far to go to be finished - I'd be worried if he were going to have to be digging around the line again!

Before









After

And last but not least... the pool is in the process of filling as I type. The garden hose has been on full-bore for the past 35 hours and we are about two-thirds full. I'm estimating the water bill at around $500 to fill that sucker. It's not a large pool but it is a good 8 feet deep. As we had suspected, the lines were bad - both the skimmer and return lines need to be replaced so we are going to hold that thought until next year... The pool guys will lay lines overground for this season and next fall or next spring we will put permanent lines in when we move the pool equipment off of the platform that's sliding down the hill and over towards the pool house that's falling down. (Another story.)

Monday, April 30, 2007

This cOld House 29

What's new this week? We met with Dick about the landscaping last Monday and although we lined out where the retaining walls were to go, the ensuing rains washed out all our work. Back to the drawing board.

We finally saw the roofers. They came last Monday and Tuesday and then disappeared. As bad as the concrete crew have been about showing up, the roofers are even worse. To compound this problem, when we first got the estimate (in December,) we were told that the roof was essentially sound and we were not advised to replace it. Instead we were told that it could (and should) be repaired using re-claimed slate to match. However, when the installer came out last week he said we should replace the whole thing and we should NOT use salvaged slate. So I called the office and said what gives? Your estimator and your installers are giving me two diametrically opposed opinions. So on Friday we had TWO estimators show up. We came up with a modified plan and I'm waiting on numbers to make a decision.

Bob Sr. is hard at work on the doors. It's beautiful weather now so working outside is wonderful. He's making the new screen doors (which he built from scratch,) fit up front today. It's a bear to get them in right since the opening is neither plumb nor square, and they have to swing, too. Still no decision on the back half of the house, (whether we have to take out the windows upstairs as well as the dining room,) and materials are looking to be a problem. 10 X 10 oak beams are hard to come by. We may have to use pressure treated and wrap it in oak or cedar.

The new garage is looking like a new garage. Dan piled a bunch of junk into it last weekend. The lift door was installed last week. They guys doing it didn't inspire a lot of confidence. The door weighs about double what a regular door weighs. They assembled it like they usually do but with the garage being brand new and no power in it yet they failed to secure a way out. There was plywood screwed from the old garage side in the cut opening between the two and the door was too heavy for the guys to lift up manually so they essentially locked themselves in the garage and had to break down the plywood to get out. All I heard was a bunch of cussing and hammering but when I saw the mess (and damage) in the old garage I figured out what happened. The blue pipes in the front are part of our elaborate drainage system that we hope will end our water problems in the garages and basement for good.

This is the final sand coat on the stucco where the old garage doors were. The guy doing it was having a heck of a time matching the texture of the existing stucco until I explained that the existing was original to the house and began its life as a smooth finish. When I described the ivy we've heard covered the place he finally understood. I told him to go ahead and just do a smooth sand coat. Dan and I both love the color of this stuff but sadly it's a little out of the vernacular for our house. But seeing this color has galvanized our decision to go with a slightly warmer cream color than we currently have. And we may use this terra cotta color somewhere on the inside... I was thinking the dining room.

Last but not least, we have a mason diligently working to build the parapet wall on top of the garage. I picked brick last week and found a hand made brick that mimicked the age and condition of what we had. The color was close, only a couple shades lighter. I think it'll work out ok. We are still deciding about what to do on the top of the wall. I wanted it scalloped, and it will be stucco, but we don't want to have to paint every year, which is what will happen if we stucco the top. Rob suggested limestone on the top and it's pretty expensive. We're still looking at options.

Thursday, February 22, 2007

This cOld House 20

Update on the gas bill pool. I've canceled the contest since I had the dates wrong for the billing cycle and didn't want to be accused of any impropriety, (Pop,) and also, I had virtually no takers! The gas bill for January 11 to February 9 (29 days,) was $641.22.

We are still crawling at a snails pace on the other open projects. Dan gave up on doing the walls ourselves, so we had Rob get his drywaller over to tape and mud the cracks. Daylight (yup, that's the name embroidered on his shirt,) did a very nice job taping up and patching where the new window frame went in as well as going over the tape job I did on the cracks and filling in some other bad areas. We will be ready to paint this weekend and will stain the floor next week with an eye on having the bath complete by the week of March 5.


Rob and Co. came by this week to build a temp wall and set a steel beam over top to hold the flexicore panels which are supposed to be installed tomorrow, (I'll believe it when I see it,) and finish off filling in and drilling through the old window openings to hold the angle iron against the kitchen wall to which the ends of the flexicore will be welded/bolted. And they shoveled out the ice and snow so they would have a nice work surface, instead of an ice work surface.

We discussed door options and Rob and Co. will be building a set of walk thru doors for the old garage where we are taking out the lift door and building a solid wall. We'll also remove the original sliding carriage house door (now fixed in place), build a wall and put a high transom window on the other side. That should go a long way in improving the temperature in the garage and kitchen/office/art room on top.

We are not looking forward to having the opening cut between the old and new garage. Concrete cutting produces a dust so fine that it's like smoke and seeps in everywhere. We know that even with measures in place, we won't be able to stop the dust from seeping in all over the house and then settling everywhere. That will happen in about a month once the inside of the garage is trimmed out and the lift door hung.


The cat finally caught a mouse (with proof) this week. The mouse was getting pretty bold considering Tommie's been on board for a couple of months. He must have lulled him into a false sense of security. I was up in the middle of the night on Tuesday and was presented with the rodent. It was fresh! Thanks, Tommie. The cat has also figured out another way into the walls/floor as he turned up filthy again this morning, with all the usual holes still blocked. If only we could train him to administer a shot of that foam sealant wherever he's finding these holes.

We have a meeting with the landscape architect on Saturday. We are going to take a look at the side lot as well, working towards a master plan for re-foresting it. (Dan wants to plant a labyrinth, complete with reflecting pool/gazing ball in the middle - I guess this goes along with his grand plan for the conservatory over top the limestone patio outside the dining room.) We hear that Seibenthalers (the go-to nursery/landscape co. in these parts,) has a kick-butt tree sale in the fall and the more you buy, the more they discount. We'll be waiting for that one.

I'll be ready with the camera tomorrow should the crane and panels show up.

Friday, February 9, 2007

This cOld House 19

This morning as I was making Cocoa for the girls, I saw our mouse. Rather, I saw a streaking blur out of the corner of my eye darting from under the fridge to under the stove - I couldn't really see it as it was going about 240 miles per hour. I called to Tommie-Cat, disturbing his breakfast. He looked at me like "whatever..." and went back to his 'cat beans' (as Naomi calls his food.)

We have contracted for storm windows for the dining room and living room. It'll be six weeks, just in time for spring!

I'm headed to Lexington this weekend with the girls, Dan is staying put to work on the bathroom. (We're responsible for painting it.) If he doesn't get it done, I'll release Rob to get on it next week. I am eager to push it along since the tub in the master bath (which we are NOT re-doing any time soon,) kind of blew out this week. Korrect Plumbing (my heroes) were able to get it back together, even 'though Dan, who harbors a secret desire to be a plumber, got to it first and essentially trashed it. Thank goodness we saved the tub valve out of the girls' bathroom - the plumber stripped the seats and stems off of it to make our tub work. But that valve won't last for long so we need to get the other tub up and running for the girls. Dan and I can survive without a tub since we have the separate shower, but the kids really need one.

I finally got a plan out of one of the landscape contractors. It wasn't at all what I wanted, so it's back to the drawing board. (Not that I can even fathom doing yard work in this cold.) Looking ahead... looking ahead....

Dan and I came across an article about retro fitting insulation in older homes. After the weather this week, we are intrigued by it. I'll point it out to Rob for his opinion when I next see him.

I've only had one taker on the gas bill pool. (See my last post.) Let me know if you are interested!

Thursday, November 30, 2006

This cOld House 6

The last couple of days have been very very busy around here. Dale started on the attic HVAC unit, cutting through ceilings for duct work and hauling the hardware upstairs to the attic. Hey did you know there's not a scrap of insulation between the attic and the the living space below??? There's a quick fix for some efficiency. I'm waiting on Rob's insulation guy (Rob - my general contractor,) to get me some numbers. Dale was missing today, working on fashioning ducts in the shop which worked out terrifically as the power (and water) was off in the house for most of the day.

Rick,(the carpenter who fixed the living room floor,) Larry and Bob Sr. have been tag-teaming on the beam in the garage. Rick and Larry built three support walls to hold up the cantilevered room over top and then mid-way through the second day Rick and then Bob worked to remove the beam that was all ate up. There were three 2 x 8 planks and a 2 x 4 involved, with one 2 x 8 remaining pretty solid. They replaced the remaining two and the 2 x 4 with three more 2 x 8 planks and hung the joists on hangers. The sub-floor was pretty ate up as well, but we can't really get to it as it is under the wall from above. Bob was confident that it wouldn't be an issue.

Tim the plumber was able to get all the water pipes out of the way, shutting down the downstairs bath until the project is done. He had to move some valves and add a couple to get it isolated and shut off, and then cut and capped the pipes. The electric remained in the way.

Right when Rick was getting down to the nitty-gritty pulling out the beam the electricians showed up. These were replacement electricians as the original guy was too busy to get to the panel to meet Bob's schedule. So Tom and crew swarmed in at noon and cut the power, ripping out the old 200 AMP panel, moving the meter and installing a new 200 AMP panel over by where the new A/C condensers will sit outside the old garage. Then they added a new 100 AMP sub-panel where the old panel was, and hooked up the rest of the house back to it. All of this took care of the main line which had to be moved out of the way of the beam replacement project, as well as various and sundry fire hazards discovered when we ripped down the drywall ceiling in the old garage. Tom is coming by tomorrow to see what all else needs to be done. (Making the plugs kid-safe, fixing the code issues in the kitchen, running new clean power to the A/V and computers, adding a phone jack so we can answer the phone in the living room.) Dan also said something about running some CAT6 (ethernet) around as well.

Rob and Co. (That's the two Rick's, Bob Sr. and Larry, so far,) will have no more to do once the beam is done until I get a firm bid on the new garage and the bathroom remodel. As it is we're about 2 good man-weeks into T & M (time and material) stuff and that makes me nervous. The living room floor had a price tag on it but they found more damage than anticipated, and I have only my own estimation on what the beam will cost us.

Tim the plumber had some good news for us in that we now have a pretty good plan on how to clean up the miles of pipes in the house. The girls bathroom is now a must do, for several reasons, but once it is done, we will have over half the house re-plumbed, (correctly and legally,) including all the supply in the basement. It will be great to get rid of all the old galvanized piping down there as it's corroding as I sit here, waiting to spring a leak. (Not to mention the 17 rusting valves in the laundry room alone.) He managed to replace the main shut off valves, install a pressure regulator and baffle, several angle stops and bring the kitchen gas valve up to code. Unfortunately when he reduced the water pressure from 115 PSI to the recommended 85 PSI, we lost all pressure to the upstairs fixtures. (The cold lines are almost completely corroded shut, which is why doing the girls' bath has moved up the priority list.)

I met with a landscape architect to work up a proposal for the front of the house when we tear it up to put in the garage. He seems to be right on track with what I outlined and I'm sure if he watches his spending, he'll do a bang-up plan for us. I meet with a different landscape architect tomorrow to do it all over again.

My other landscape guy dropped by today, (the one who did the clean-up on the yard) and I grabbed him to talk about the stretch of mud along the back of the house. He's working up numbers for me for putting flagstones down. Dan wants to get a second opinion on the catalpa tree, so I'll be calling around tomorrow to get someone out. It is not an immediate need - we can probably wait a year or two before we have to yank it down.

Today the gutters were cleaned for the last time this season. All the trees are now bare so we no longer have to fear a gutter back-up, (provided we don't have a problem with an ice dam.)

All in all we've had a pretty good week with no real surprises. (Although when Tim grabbed an old recirculating line to indicate it needed to be removed, it broke free of its moorings and fell on his head. He had to temporarily tack it back up.) As it turns out, once the termite-beam was removed, the joists were found to be solid, so we didn't have to replace any of them. I haven't had the heart to tell Rick we still have a soft spot in the living room floor behind a duct that he probably didn't see. (He is nursing broken ribs from a car accident last week and I can't imagine shimmying around my crawlspace would be very good for the ailment.) And Other Rick, (the one who worked on all the doors earlier in the week,) appears to have glued my back door shut, which will have to be freed. That back door really needs to be replaced, but we are holding off on frivolous stuff like that. It works just fine for now, (if you put your shoulder into it.)

I'm actually starting to see some light at the end of the tunnel. Of course, this tunnel is a detour I was forced into on my way to building a garage. Still, it's good we are taking care of these things in such a manner that they shouldn't bother us for another 30 years or so. I'm really quite thrilled that the plumbing has presented itself to be a short term project that won't be nearly as difficult as I had feared. And Dan, who is the voice of reason (budget,) also agrees.